Saturday, July 31, 2010

Caramel Apple Station

more time available for the account energy 2010


No more 31 December 2010, but June 30, 2011. Sled the date by which they will become operational photovoltaic systems in order to continue enjoying the current energy bill. The novelty in an amendment dl the Energy approved the Senate that makes a soft transition between the two incentive schemes by protecting them from delays in the connection.

No more 31 December 2010, but June 30, 2011. Sled the date by which they will become operational photovoltaic systems in order to continue to enjoy the energy tariffs for the second account, the current one and that it will be up later this year.
The twist comes with the approval last week in the Senate, an amendment to the so-called "decree of energy" (dl 8 July 2010, n. 105) that will go through both the House next week but, being " armored, should not be changed.

Amendment, which amends the act establishing that existing incentives had access to only those plants came into operation by December 31, 2010, (ie e-paragraph 1 of Article 2 of Law Decree 25 January 2010 , No. 3, with amendments, into law March 22, 2010, 41) and replaces it this way: "The tariffs referred to in Article 6 of the Decree of the Minister of Economic Development, February 19, 2007 (...) are recognized to all persons who, in accordance with the provisions of Article 5 of the ministerial decree, have concluded, by December 31, 2010, installation PV plant, has provided information to the competent authority to be given to the operator of the network and the Manager of Electrical Services-GSE Spa, by the same date, the completion of work and enter into operation by June 30, 2011. "

So if the decree will pass as amended, to enjoy the current incentives (rather than revised down the energy bill in 2011) no longer required that the request is made to Enel in time (ie 15 November 2010 for simple systems) and that the plant comes into operation by December 31, 2010. Just that by then the plant is finished (it will certify the affidavit by a qualified technician) and the connection request submitted, at which point it becomes operational there will be time just until June 30.

inspections and audits to ensure that no cheats are delegated to the operator of the network and the GSE, and the Authority for electricity and gas, within 90 days from the conversion of the decree, must draw up rules to prevent 'acts of booking network capacity for systems using renewable sources for which have not occurred within the time given the conditions of practical implementation of the initiatives, with reference to connection requests already assigned "

" The amendment explains Qualenergia.it- Senator Francesco Ferrante (PD) - has been introduced to avoid that because of delays in the connection by the network operator many plants lose the right to access the old energy bill. With such a wide window between the demand for connection and the date by which the system must be operational, and the rules guarantee that the Authority will establish, this should not happen again. "In short, an amendment to prevent traffic jams in connection procedures with which the transition from second to third in tariff will be softer.

Under the incentive scheme for the next energy bill will fall, therefore, only plants that are ready and will not be made la richiesta di connessione entro il 31 dicembre 2010 o che comunque non saranno entrati in esercizio oltre il 30 giugno 2011.
Questi – come spiegato su queste pagine nell’illustrare le modifiche introdotte andranno incontro a riduzioni delle tariffe incentivanti tra 10 e il 25% per gli impianti installati su edifici e tra il 13 e il 27% circa per gli altri impianti.